WEBVTT

1
00:00:23.580 --> 00:00:24.980
You

2
00:00:35.520 --> 00:00:41.700
Oil is on the move in a growing progressive American industry which began with a single well

3
00:00:41.700 --> 00:00:48.920
drilled by Colonel Drake in Pennsylvania in 1859. Today nearly a million and a half wells have

4
00:00:48.920 --> 00:00:55.400
been drilled in the United States. Over 2,000 products come from petroleum and oil comes from

5
00:00:55.520 --> 00:01:07.640
many parts of our nation to keep America on wheels. Yes, oil is on the move. Oil is under

6
00:01:07.640 --> 00:01:15.480
our lands, our seas, and oil is in the Rockies. Oil is in Nebraska, Colorado, Montana, and Wyoming.

7
00:01:17.480 --> 00:01:23.160
The Denver-Julesburg Basin had been opened. The new adena field in Colorado was being developed,

8
00:01:23.160 --> 00:01:30.000
and there was increasing crude oil production in Kansas. Now efficient methods of crude oil

9
00:01:30.000 --> 00:01:36.040
transportation were immediately necessary. Officials of the Pure Oil Company and Sinclair

10
00:01:36.040 --> 00:01:41.900
Pipeline Company felt that an important contribution could be made by the building of a large capacity

11
00:01:41.900 --> 00:01:49.440
18 and 20 inch crude oil line to carry crude into major refining centers. This large diameter

12
00:01:49.440 --> 00:01:55.980
pipeline started at Marino, Colorado. Crude oil from the Denver-Julesburg Basin could be moved

13
00:01:55.980 --> 00:02:01.940
almost by gravity flow through Colorado and Kansas through areas already producing or known

14
00:02:01.940 --> 00:02:08.420
to have possible production. This new line was to join Sinclair's Chicago Big Inch at Humboldt,

15
00:02:08.420 --> 00:02:15.240
Kansas. Thus, crude oil from all of the Rockies and the rapidly developing nearby areas could

16
00:02:15.240 --> 00:02:23.040
be made available to great refining centers. The Arapahoe was to be its name. The decision was

17
00:02:23.040 --> 00:02:28.060
made and surveyors then started plotting the route, which up to then had been nothing more

18
00:02:28.060 --> 00:02:37.280
than a penciled line on a map. Right of way for the line had to be acquired, over 1,200 landowners

19
00:02:37.280 --> 00:02:49.340
were involved, some nearby and some far away. Rivers had to be sounded, currents measured,

20
00:02:49.420 --> 00:02:58.740
and the methods of crossing determined. More than 79,000 tons of high tensile, carefully tested

21
00:02:58.740 --> 00:03:04.100
steel pipe and casing had to be fabricated in steel mills and delivered along the route of the

22
00:03:04.100 --> 00:03:14.340
line. Many pipe yards at convenient points had to be established in Colorado and Kansas. Each one

23
00:03:14.340 --> 00:03:20.500
had to be handed to the spreads or crews working the area. There were actually five separate

24
00:03:20.500 --> 00:03:29.880
construction spreads or operating areas over the length of the Arapahoe. All kinds of terrain,

25
00:03:29.880 --> 00:03:38.800
from the flint hills of Kansas to rich prairie soil, had to be prepared for ditching. Access

26
00:03:38.800 --> 00:03:43.980
gates along the entire construction route had to be cut into the regular fencing to allow for the

27
00:03:43.980 --> 00:03:56.800
movement of men and machines. Modern ditching machines did the bulk of the trench digging.

28
00:04:03.300 --> 00:04:08.960
Most of the route of the Arapahoe was across soft, loamy soil that was placed neatly on the

29
00:04:08.960 --> 00:04:16.260
offside of the ditch so that it could easily be replaced after the pipe was laid in. With

30
00:04:16.260 --> 00:04:20.780
construction beginning late in August and operation of the Arapahoe hoped for by December,

31
00:04:21.500 --> 00:04:27.300
all phases of construction, including the delivery station at Humboldt, had to begin almost simultaneously.

32
00:04:31.380 --> 00:04:37.340
When the land became slightly rocky or a bit on the ledgy side, the back hose took over from

33
00:04:37.340 --> 00:04:49.000
the ditching machines. When the back hose bogged down, the heavy flint and sandstone had to be

34
00:04:49.000 --> 00:04:59.000
attacked by diesel cats attached to a router. Something had to give. Most of the country

35
00:04:59.000 --> 00:05:05.700
crossed by the Arapahoe is valuable farm or grazing land. Arapahoe officials specified that such

36
00:05:05.700 --> 00:05:12.040
land must be protected while the line was under construction. When mechanical means failed to

37
00:05:12.040 --> 00:05:19.680
budge earth or rock, the powder monkey was called into action. For farmed or grazed land, many light,

38
00:05:19.680 --> 00:05:33.900
gently nudging shots were employed. For land not so used, fewer and larger charges.

39
00:05:39.540 --> 00:05:41.980
And where very rocky terrain was encountered,

40
00:05:49.820 --> 00:05:57.260
a big one generally did the job. Rarely did the path of the Arapahoe pass near established

41
00:05:57.260 --> 00:06:10.060
routes of travel. All pipe and casing had to be trucked from the nearest pipe yard over all kinds

42
00:06:10.060 --> 00:06:23.260
of roads to the company's right of way. Many of the workmen on this gigantic job of pipeline

43
00:06:23.260 --> 00:06:27.180
construction came from communities near the root of the Arapahoe.

44
00:06:38.760 --> 00:06:51.660
After stringing came the lining up of the pipe on skids. The direct path of the Arapahoe took it

45
00:06:51.870 --> 00:06:58.470
or over all kinds of obstructions. Under was the order for a place in Kansas with the trunk lines

46
00:06:58.470 --> 00:07:21.850
of a railroad parallel to federal highway. This crossing, as it is called, involved

47
00:07:21.850 --> 00:07:27.250
boring under the highway and railroad so as not to hold up service for one single moment,

48
00:07:27.650 --> 00:07:29.470
not even slow it to Iota.

49
00:07:47.750 --> 00:07:52.550
After the proper boring was completed, the casing which carried the auger remained in

50
00:07:52.550 --> 00:07:57.730
the opening made under the obstruction as protection for the line carrying the crude oil.

51
00:07:59.470 --> 00:08:05.590
It was a tough, ticklish job that involved many men and machines working smoothly with one another.

52
00:08:13.750 --> 00:08:20.030
Hills and valleys presented very few problems to the line contractors. In order that the pipe

53
00:08:20.030 --> 00:08:24.790
fit into its tailor-made trench, it had to be bent to conform with a slope of many a hill.

54
00:08:33.730 --> 00:08:46.730
Before welding could begin, beveled edges had to be buffed and cleaned. Pulling the

55
00:08:46.730 --> 00:08:49.570
line of clamps into place was another exacting operation.

56
00:09:05.930 --> 00:09:10.090
First, a tack weld or stringer bead to hold the aligned position.

57
00:09:17.490 --> 00:09:23.550
Then a filler weld or first pass. Actually, a weld over a weld almost half the thickness

58
00:09:23.550 --> 00:09:31.110
of the pipe. Each welder's working number was stamped on the welds he made. Then preparation

59
00:09:31.110 --> 00:09:37.370
for the windup of the welding operation. The final or tack weld actually stands a bit above

60
00:09:37.370 --> 00:09:48.830
the level of the pipe. The high-intensity electric arc makes a band around the previous welds.

61
00:09:57.070 --> 00:10:00.750
So that no invisible flaws would remain to weaken a weld,

62
00:10:01.350 --> 00:10:05.870
thousands of welds along the Arapaho were x-rayed shortly after they were finished.

63
00:10:18.250 --> 00:10:22.790
Where there was a defective weld, it had to be corrected before placing the line in the ditch.

64
00:10:30.390 --> 00:10:35.690
Once all welds had been x-rayed, inspected and accepted, the line was made ready for

65
00:10:35.690 --> 00:10:41.430
an operation that would extend its life for at least half a century. The cleaning and

66
00:10:41.430 --> 00:10:46.150
brushing machine first removed all rust and foreign particles and was immediately followed

67
00:10:46.150 --> 00:10:50.910
with a prime coat of asphalt for additional protection from the ravages of moisture,

68
00:10:50.910 --> 00:10:57.250
cold and heat. Then followed the flexible nimble-fingered wrapping machine, applying

69
00:10:57.250 --> 00:11:03.030
another generous coat of asphalt and in the same operation completely covering the line with a

70
00:11:03.030 --> 00:11:07.910
specially prepared asbestos belt wrapping. Thus many years were added to the life of the line

71
00:11:07.910 --> 00:11:09.670
through the prevention of corrosion.

72
00:11:18.530 --> 00:11:24.010
In every phase of construction, nothing was left to chance. To check the completeness of

73
00:11:24.010 --> 00:11:29.450
the wrapping machine's work, a device known as a holiday detector or Jeep as the workmen call it,

74
00:11:29.750 --> 00:11:31.610
was drawn over every foot of wrapping.

75
00:11:38.070 --> 00:11:41.910
Where defects in coating were found, they were repaired by hand.

76
00:11:48.730 --> 00:11:53.030
Because settling rock in the ditches could possibly bring great pressure to bear on the

77
00:11:53.030 --> 00:11:58.050
ordinary wrapping where it crossed through rocky ditches, a second protective coating was used.

78
00:11:59.650 --> 00:12:05.190
Called a rock shield, it was applied by hand, bound with steel straps,

79
00:12:18.490 --> 00:12:21.230
once again doped, this time by hand.

80
00:12:28.330 --> 00:12:30.750
At intervals dictated by the engineering staff,

81
00:12:31.290 --> 00:12:34.230
electrolysis test connections were installed with thermal welds.

82
00:12:46.990 --> 00:12:52.770
To complete the control of electrolysis, rectifying units were installed at proper locations.

83
00:12:59.490 --> 00:13:02.490
Dry washes and creeks, which were known to have a history of flooding,

84
00:13:02.490 --> 00:13:08.070
were treated as though they flowed year-round. Huge concrete river weights, weighing more than

85
00:13:08.070 --> 00:13:13.190
half a ton each, were placed in calculated intervals throughout the actual crossing area.

86
00:13:14.810 --> 00:13:19.910
This was done because flash floods have a way of deepening channels, and the additional weight

87
00:13:19.910 --> 00:13:24.230
provides negative buoyancy to keep the line from floating and washing out.

88
00:13:26.150 --> 00:13:31.190
While the pipeline crews were busy, tank construction crews were also building working

89
00:13:31.190 --> 00:13:35.230
tanks at the pumping stations. There were electric plate handling machines that moved

90
00:13:35.230 --> 00:13:41.810
one ton plates about like playing cards, hydraulic plate alignment devices that did the work of five

91
00:13:41.810 --> 00:13:56.770
men, automatic welding machines that seemed to crawl around the surface of the rising

92
00:13:56.770 --> 00:14:03.710
tanks like huge spiders. One inside, another outside. They're operators connected by intercom

93
00:14:03.710 --> 00:14:10.070
systems. These and many other construction models all combined at Marino Station to produce three

94
00:14:10.070 --> 00:14:15.570
huge working tanks, each with a capacity of over five million gallons of crude oil.

95
00:14:24.470 --> 00:14:29.370
The middle of September saw some of the spreads or crews completing their sections,

96
00:14:30.430 --> 00:14:33.110
joining them and lowering in as they progressed.

97
00:14:43.710 --> 00:14:48.590
The early part of October saw temporary pipe bridges built for the blasting crews.

98
00:14:53.550 --> 00:14:58.630
With the dynamite charges in place clear across the stream, the crew cleaned up and brought wires

99
00:14:58.630 --> 00:15:06.430
to shore. The pipe ridge was towed to safety, the whereabouts of all personnel checked,

100
00:15:07.210 --> 00:15:08.850
and the order given to fire.

101
00:15:19.270 --> 00:15:23.250
Drag lines removed the mud and rock from the blasted underwater ditch.

102
00:15:30.850 --> 00:15:36.050
Then with half ton river weights already installed and a half dozen cats urging it on,

103
00:15:36.510 --> 00:15:40.510
another section of the Arapaho joined the category of finished.

104
00:15:46.710 --> 00:15:51.890
When other pipelines cut across the path of the Arapaho, the line was installed at least

105
00:15:51.890 --> 00:15:58.450
two feet below the existing carrier. In the case of other obstacles such as irrigation ditches,

106
00:15:58.450 --> 00:16:03.210
overhead crossings were made if the span did not exceed 60 feet in length.

107
00:16:11.710 --> 00:16:15.210
A chill of fall was felt when the final backfilling took place.

108
00:16:27.710 --> 00:16:30.870
Crews installing new fence had to face sharp winds.

109
00:16:37.370 --> 00:16:41.010
The chilly hand of Jack Frost was seen in the fields of eastern Kansas,

110
00:16:41.010 --> 00:16:44.810
where but a few short weeks ago both men and machines had been.

111
00:16:51.950 --> 00:16:55.170
Snow had already fallen on the high plains of Colorado,

112
00:16:55.750 --> 00:17:00.350
when the first crude started to flow eastward from the Marino station early in December.

113
00:17:18.610 --> 00:17:23.730
The Arapaho today represents an up-to-the-minute example of engineering skill,

114
00:17:24.090 --> 00:17:27.890
design, and construction in modern pipeline practice.

115
00:17:33.890 --> 00:17:39.810
This project, conceived by the officials of the Sinclair Pipeline Company and the Pure Oil Company,

116
00:17:39.810 --> 00:17:45.310
to keep America on wheels was given the designation Defense Department Project

117
00:17:45.310 --> 00:17:51.110
by the United States government. It stands ready and available should needs of war arise.

118
00:17:51.650 --> 00:17:56.270
It makes available to the refining centers vast quantities of crude oil.

119
00:17:56.970 --> 00:18:02.890
How fitting then that it should be named after a brave group of Native Americans, the Arapaho.

120
00:18:11.690 --> 00:18:13.090
you

